Texas Comptroller of Public Accounts
CAPPS - Report to the 83rd Legislature

Appendix A: Timelines

Financials Timeline

Financials Project Timeline

Though the activities listed end at specific times, they may be run concurrently.

November 2009

Deloitte selected as the Single Implementation Vendor

December/January 2009

Established starting system (CPA/ISAS 9.0)

April 2010

  • Completed upgrade from 9.0 to 9.1
  • Completed Requirements Gathering

June 2010

Completed Fit/Gap against vanilla 9.1

August 2010

Completed process designs

February 2011

Completed development objects

June 2011

Completed testing activities

July 2011

Completed user acceptance

August 2011

Completed cutover activities

September 1, 2011

DIR and CTTS Go Live

November 2011

CPA and TDI Kickoff

January 2012

Completed baseline configuration

March 2012

Built updated code line

May 2012

Completed system test

June 2012

Completed user acceptance

July 2, 2012

CPA and TDI Go Live

October 2012

Began readiness assessment for TxDOT

HR/Payroll Timeline

HR/Payroll Project Timeline

Though the activities listed end at specific times, they may be run concurrently.

November 2009

Deloitte selected as the Single Implementation Vendor

December/January 2009

Establish starting system (HHSC/accessHR 8.3)

April 2010

Complete Requirements Gathering

May 2010

Complete Fit/Gap against vanilla 9.1

November 2010

Project transitioned from Deloitte to NgA

April 2011

Completed upgrade from 8.3 to 8.9

July 2011

Design complete

March 2012

Build complete

July 2012

Completion of User Acceptance Testing

Nov. 8, 2012

Go Live